As part of Trowbridge Future High Street Fund Scheme, work is programmed for Church Street and Union Street.
This is due to commence on the 31st October with the first actions being the removal of the signal equipment and existing traffic islands. Following that, the works will begin on the north-western footway (shown as A bound by purple line below) then continue around the junction in a clockwise direction, with works in Church Street east (shown as ‘D’ outside of the shops and Church) taking place after Christmas.
Click here to see the Letter issued to Residents. The letter provides information regarding the scheme, construction phasing and duration.